Chartered surveyor based in Kingston upon Thames Call or text 07876 745432

Home / Party Wall Notices

Free Party Wall Notices

Fill in the short form below and this page writes your party wall notices for you, with an acknowledgement form and a covering letter for your neighbour, and a plain guide to serving them.

Do you need a notice?

Under the Party Wall etc. Act 1996, you must give your neighbours written notice before starting certain building work. There are three kinds of notice:

  • Line of junction notice (section 1): building a new wall on, or up against, the boundary line where there is no shared wall. One month's notice.
  • Party structure notice (section 3): work to a wall, floor or other structure you already share, such as cutting in steel beams for a loft conversion or extension, removing a chimney breast from a party wall, raising the wall, underpinning it, or inserting a damp-proof course. Two months' notice.
  • Adjacent excavation notice (section 6): digging foundations within 3 metres of your neighbour's building and deeper than its foundations, or within 6 metres where the dig would cross a line drawn down at 45 degrees from the bottom of their foundations. One month's notice.

Many projects need more than one. A rear extension often needs a party structure notice and an adjacent excavation notice. Minor work, such as putting up shelves, fitting sockets or replastering, doesn't usually need notice.

This page gives general guidance only. It isn't legal or professional advice on your project, and you are responsible for the details you enter. A notice with the wrong details or served on the wrong people may not be valid. If you're unsure, ask a party wall surveyor before you serve.

1. Which notices do you need?

Tick every one that applies.

2. You and your property

Name everyone who owns your property. Every owner should sign the notices.

3. Your neighbour

If you can't find out who owns the property, leave the names blank and the notice will be addressed to "The Owner". If the neighbouring property has separate owners, such as a freeholder and a leaseholder, prepare a separate set for each: change the names and make the documents again.

4. Dates and surveyor

If your neighbour doesn't consent, one agreed surveyor acting impartially for you both is usually the quickest and cheapest route. Leave this blank if you haven't chosen one.

5. Your documents

Make each document, check it carefully, then download or print it. Send your neighbour each notice, the acknowledgement form and the covering letter together.

Serving the notices

  • Who: every owner of the neighbouring property. That includes the freeholder and anyone with a lease of more than a year. Joint owners can be named on the same notice.
  • How: hand it to them, or post it to their home or business address (for a company, its registered office). If you can't find out who the owner is, address it to "The Owner" and fix it somewhere easily seen on the property. Use email only if they've said in writing that they'll accept notices by email.
  • When: the notice period runs from the day the notice is served. If you post it, allow a few extra days.
  • Records: keep a signed copy of everything you send, and proof of posting or delivery.

What happens next

Your neighbour has 14 days to reply. They can:

  • Consent. The work can go ahead once the notice period ends, or sooner if they agree in writing. They keep the right to have any damage put right, so it's sensible to take dated photographs of their side of the wall before you start, with their permission.
  • Dissent and agree a surveyor. One agreed surveyor prepares a party wall award setting out how the work is to be done.
  • Dissent and appoint their own surveyor. Each of you appoints a surveyor, and the two surveyors agree the award.

If they don't reply within 14 days, the Act treats this as a dispute, and surveyors need to be appointed. As the owner carrying out the work, you would normally pay the surveyors' reasonable fees.

A party structure notice or adjacent excavation notice runs out if the work hasn't started within 12 months. Party wall notices are separate from planning permission and Building Regulations approval, which you may also need.